Taseko Mines improves cornerstone operation’s economics, extends life
TORONTO (miningweekly.com) – An updated mine plan for base metals miner Taseko Mines’ 75%-owned Gibraltar openpit copper/molybdenum mine, in south-central British Columbia, has improved the operation’s financial metrics, lifted reserves and extended the mine life.
The latest mine plan, the result of a detailed, six-month engineering study forming the basis of an updated National Instrument 43-101-compliant reserve, featured a 50% decrease in the strip ratio.
The study reduced the average strip ratio to 1.9:1 from 4.3:1, which would lower mining costs by reducing the volume of waste mined.
"Every point of strip ratio is equal to about 31-million tonnes of waste that does not need to be mined annually and, at $1.85/t mined, amounts to roughly $57-million of annual savings," Taseko president and CEO Russell Hallbauer advised.
During a March 26 telephone call with analysts, he noted that the previous mine plan, with its higher strip ratio, bottlenecked mining operations by limiting the release of ore and by maintaining a tight operating area in the mining zone.
As at December 31, Gibraltar had total proven and probable reserves over five openpits of 749-million tonnes, grading 0.256% copper and 0.008% molybdenum, or 0.272% copper equivalent. These reserves were contained within measured and indicated resources of 1.09-billion tonnes, averaging 0.254% copper and 0.008% molybdenum. These figures reflected a reduced cutoff grade of 0.15%, down from 0.2%, which offset the reduced strip ratio.
Under the new mine plan, Gibraltar, currently Canada’s second biggest opencast mine, would produce 3.3-billion pounds of red metal and 62-million pounds of molybdenum. The operation’s average yearly output would be about 138-million copper and 2.6-million pounds of molybdenum, at a milling rate of 85 000 t/d. The resources would support 24 further years of operation.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation