SALT LAKE CITY (AP) -- The Army Corps of Engineers says it has found electrical problems at the National Security Agency's $1.7 billion data center in Utah that could delay the new facility's long-awaited opening this fall. The data center is filled with ...
Yahoo Finance · 10/8/2013
The $1.7 billion facility, the NSA's largest data-storage center in the U.S., has generated much discussion and concern in Utah since the agency chose the location over 37 others because electricity is cheaper here and land more easily available.
Yahoo News · 2/13/2014
The National Security Agency will be using the treated wastewater of Howard County, Md. to cool systems inside the agency’s new data center at Fort Meade, the Baltimore Sun reported Dec. 31. Matthew Hay Brown writes the NSA plans to invest $40 …
Executive Gov · 1/13/2014
Utah's NSA Data Center in Bluffdale, Utah. Electrical failures are complicating the opening of the National Security Agency’s largest data storage center. SALT LAKE CITY -- Electrical problems have stalled the planned opening this fall of the nation's ...
New York Daily News · 10/8/2013
On Sunday, November 24th, the NSA data collection center was targeted by US citizens angered by violations of their first amendment rights to free speech and association, and their rights of privacy protected by the fourth amendment. The citizens lifted a ...
OpEdNews · 11/27/2013
A bill filed in the Utah state house yesterday would deny critical resources - like water - to the massive NSA data center there should it pass. House Bill 150 (HB150), introduced by Rep. Marc Roberts, would require that the water being supplied to the NSA ...
Telepresence Options · 1/24/2015
The National Security Agency's $2 billion mega spy center is going up in flames. Technical glitches have sparked fiery explosions within the NSA's newest and largest data storage facility in Utah, destroying hundreds of thousands of dollars worth of ...
The Fiscal Times · ByBrianna Ehley · 10/8/2013
WASHINGTON — Don't look for balloons or a big "Grand Opening" sign outside the National Security Agency's new Utah Data Center. The facility is expected this fall to quietly begin sucking in massive amounts of information for the intelligence community ...
Denver Post · 9/28/2013
The price tag (News - Alert), by the way, was estimated at $100 trillion. That being said, the NSA’s new data center is not going to store a Yottabyte of data. Forbes managed to get a hold of the blueprints for the new NSA data center. The building is ...
TMCnet · 8/9/2013
Power surges with no clear fix led NSA to delay the opening of a major data center in Utah. (Stock image) The opening of the National Security Agency's $1.5 billion Utah Data Center has been delayed for a year, according to a Wall Street Journal report ...
The Business of Federal Technology · 10/9/2013