Power surges with no clear fix led NSA to delay the opening of a major data center in Utah. (Stock image) The opening of the National Security Agency's $1.5 billion Utah Data Center has been delayed for a year, according to a Wall Street Journal report ...
The Business of Federal Technology · 10/9/2013
The National Security Agency’s massive data center in Utah has been plagued by electrical problems that have delayed the opening of the 1 million square foot campus. The Wall Street Journal reports that there have been 10 incidents of arc flash ...
WHIR · 10/8/2013
(AP) The Army Corps of Engineers says it has found electrical problems at the National Security Agency's $1.7 billion data center in Utah that could delay the new facility's long-awaited opening this fall. The data center is filled with super-powered ...
Times-Leader · 10/8/2013
More from Bing News
BLUFFDALE, Utah (AP) -- The nation's new billion-dollar epicenter for fighting global cyberthreats sits just south of Salt Lake City, tucked away on a National Guard base at the foot of snow-capped mountains. The long, squat buildings span 1.5 million ...
TPM · 6/14/2013
The Army has awarded a $1.2 billion contract to a construction consortium to build a spacious new data center in Utah for the National Security Agency's (NSA's) cybersecurity effort. The U.S. Army Corps of Engineers said it awarded the contract to Balfour ...
Dark Reading · 9/29/2010
At the end of June, a coalition led by the Electronic Frontier Foundation trolled the NSA by air, hiring a huge blimp to hover over the agency's new data center in Utah. Now, the EFF has released a huge image of the high-security center. It's both banal ...
gizmodo.in · 7/10/2014
Talks with the National Security Agency may lead to a new University of Utah curriculum that would prepare students for jobs in the massive data center the spy agency is building at Camp Williams. Wired postulates that in order to monitor global Internet ...
KSL · BySteve Fidel · 3/17/2012
WASHINGTON — Don’t look for balloons or a big "Grand Opening" sign outside the National Security Agency’s new Utah Data Center. The facility is expected this fall to quietly begin sucking in massive amounts of information for the intelligence ...
Reporter · 9/29/2013
The National Security Agency's new data center in Utah was built for a 65 megawatt load, making it one of the world's largest data centers. But it has had a rough start. The $1.53 billion data center was built on a "very aggressive" schedule, according to ...
Computer World · ByPatrick Thibodeau · 10/17/2013
The NSA’s new data-storage center in Utah has suffered a series of mysterious meltdowns in the past year. Officials told the Wall Street Journal that 10 fiery explosions, known as arc-fault failures, have ripped apart machinery, melted metal and ...
Time U.S. · 10/8/2013