Mass Clean Energy Center Loses 20 Million Plus On Wind Turbines

Suffolk County Civil Jury Trial Case # 1684CV02305 Monday, June 14, 2019 - Jury Finds Against MassCEC 20 Plus Million

New Bedford Ocean Wind  Terminal -Hurricane Gates Only 120 Foot Opening -No Wind Turbine Jack Up Barges Fit
New Bedford Ocean Wind Terminal -Hurricane Gates Only 120 Foot Opening -No Wind Turbine Jack Up Barges Fit (Image Credit Frank Haggerty)

JUNE 18, 2019

06/14/2019

Event Result:: Jury Trial scheduled on:
06/14/2019 09:00 AM
Has been: Held as Scheduled

Find out what's happening in Falmouthwith free, real-time updates from Patch.

06/17/2019
Exhibits returned per Order of the Clerk

Exhibit Receipt
Sent On: 06/17/2019 08:53:26

Find out what's happening in Falmouthwith free, real-time updates from Patch.

1684CV02305
Business Litigation
07/22/2016
Actions Involving Business Entities and Government
Cashman Dredging and Marine Contracting Co LLC
Plaintiff

Cashman Dredging and Marine Co., of Quincy, and New Jersey-based Weeks Marine Inc. filed the civil complaint July 22,2016 in Suffolk County Superior Court in Boston.

The lawsuit alleges that MassCEC not only misrepresented the scope and conditions of dredging work, but also “repeatedly denied” requests for change orders on the project.

August 2, 2016 • Massachusetts
Contractors suing Marine Commerce Terminal manager for $23 million

Credit: Harbor dredgers say South End facility's publicly funded manager, MassCEC, understated scope of project | By Mike Lawrence | Aug. 1, 2016 | www.southcoasttoday.com ~~

https://www.wind-watch.org/news/2016/08/02/contractors-suing-marine-commerce-terminal-manager-for-23-million/