Electricity supply is becoming the latest chokepoint to threaten the growth of artificial intelligence, according to leading tech industry chiefs, as power-hungry data centres add to the strain on grids around the world.

Billionaire Elon Musk said this month that while the development of AI had been “chip constrained” last year, the latest bottleneck to the cutting-edge technology was “electricity supply”. Those comments followed a warning by Amazon chief Andy Jassy this year that there was “not enough energy right now” to run new generative AI services.

Amazon, Microsoft and Google parent Alphabet are investing billions of dollars in computing infrastructure as they seek to build out their AI capabilities, including in data centres that typically take several years to plan and construct.

But some of the most popular places for building the facilities, such as northern Virginia, are facing capacity constraints which, in turn, are driving a search for suitable sites in growing data centre markets globally.

“Demand for data centres has always been there, but it’s never been like this,” said Pankaj Sharma, executive vice-president at Schneider Electric’s data centre division.

At present, “we probably don’t have enough capacity available” to run all the facilities that will be required globally by 2030, said Sharma, whose unit is working with chipmaker Nvidia to design centres optimised for AI workloads.

“One of the limitations of deploying [chips] in the new AI economy is going to be . . . where do we build the data centres and how do we get the power,” said Daniel Golding, chief technology officer at Appleby Strategy Group and a former data centre executive at Google. “At some point the reality of the [electricity] grid is going to get in the way of AI.”

Column chart of $bn showing Microsoft, Amazon and Alphabet's collective capital expenditure on cloud is expected to grow

The power supply issue has also fuelled concerns about the latest technology boom’s environmental impact.

Countries worldwide need to meet renewable energy commitments and electrify sectors such as transportation in response to accelerating climate change. To support these changes, many nations will need to reform their electricity grids, according to analysts.

The demands on the power grid are “top of mind” for Amazon, said the company’s sustainability chief, Kara Hurst, adding that she was “regularly in conversation” with US officials about the issue.

Data centres — industrial buildings, often covering large areas of land, that house the physical components underpinning computer systems, such as cabling, chips and servers — are part of the backbone of computing.

Research group Dgtl Infra has estimated that global data centre capital expenditure will surpass $225bn in 2024. Nvidia’s chief executive Jensen Huang said this year that $1tn worth of data centres would need to be built in the next several years to support generative AI, which is power intensive and involves the processing of enormous volumes of information.

Such growth would require huge amounts of electricity, even if systems become more efficient. According to the International Energy Agency, the electricity consumed by data centres globally will more than double by 2026 to more than 1,000 terawatt hours, an amount roughly equivalent to what Japan consumes annually.

“Updated regulations and technological improvements, including on efficiency, will be crucial to moderate the surge in energy consumption from data centres,” the IEA said this year.

US data centre electricity consumption is expected to grow from 4 per cent to 6 per cent of total demand by 2026, while the AI industry is forecast to expand “exponentially” and consume at least 10 times its 2023 demand by 2026, said the IEA.

Line chart of Total data centre market operational capacity (MW) showing The global data centre market is growing and consuming more power

Even before the generative AI boom, some major markets were struggling to keep up with demand. It can take years for new renewable energy projects such as wind farms to gain regulatory approval and be connected to the grid. There is also a need in some places to build new transmission lines that carry electricity from one point to another.

In northern Virginia, the world’s largest data centre hub, power provider Dominion Energy paused new data centre connections in 2022 while it analysed how to deal with the jump in demand, including by upgrading parts of its network.

In October, the company said in filings to a Virginia regulator that it was experiencing “significant load growth due to data centre development” and that growing power demands presented a “challenge”.

In response to the demand, authorities in jurisdictions including Ireland and the Netherlands have sought to limit new data centre developments, while Singapore recently lifted a moratorium.

Developers are looking to build sites in growing areas such as the US states of Ohio and Texas, regions of Italy and eastern Europe, Malaysia and India, according to analysts.

Finding appropriate sites can be challenging, with power just one factor to consider among others such as the availability of large volumes of water to cool data centres.

“For every 50 sites I look at, maybe two get to the point where they may be developed,” said Appleby Strategy’s Golding. “Folks are sifting through large numbers of properties.”

The concerns have driven interest among data centre developers in options such as onsite power generation and nuclear energy, with Microsoft this year hiring a director of “nuclear development acceleration”.

Copyright The Financial Times Limited 2024. All rights reserved.
Reuse this content (opens in new window) CommentsJump to comments section

Follow the topics in this article

Comments